Illustrative case #2

The advantage of foresight

Protect your profitability before the first brick is laid.*

11-20%

Projected steel gap

COP 250M-500M

Anticipated cost overrun

30%

Units left to sell

The situation

Imagine one of your most important projects reaches a key milestone: sales hit 70%, the project breaks even, and it meets the bank’s conditions for releasing the construction loan.

The budget

Steel had been trending down, so your budgeting team reasonably allocated:

COP 3,950/kg

Unit price, including VAT

600 t

Metric tons required

COP 2,370M

Total steel budget

What the model shows

To align the budget with the market and where it’s headed, your team factors in two variables that are usually analyzed separately:

Global steel market

Suppose global demand picks up and steel prices rise 3% in dollar terms over the next year.

Exchange rate

Suppose, too, that the exchange rate climbs from COP 3,190 per dollar to somewhere between COP 3,500 and COP 3,800.

The combined effect

Modeled together, the two factors don’t add up: they multiply. In pesos, steel wouldn’t rise 3% but anywhere from 11% to 20%.

COP 3,950/kg

Initial budget

COP 4,370-4,750/kg

Projected scenario

11-20%

Compounded gap

The advantage of knowing early

An 11% to 20% jump in steel sets off alarm bells: that’s up to COP 500 million more on a single material. But your team sees it coming with 70% of the project sold, not 100%, and can still act:

  • Reprice the units still for sale.
  • Negotiate or buy steel sooner, before prices rise.
  • Give the banks an updated budget backed by market data.

That’s the difference between absorbing a cost overrun and managing it.

What would this analysis look like for your next project’s budget?

Book a demo